Execution contract

Construction of Pump station DE289 and disaster pipeline

Customer: LKAB
Year: 2016
Total: 20 miljoner SEK
Contractor type: Execution contract

Earthworks as below Excavation work, pipeline bed, protective fill, remaining fill. Laying of line approx. 600 meters with dimension 1200-250mm, Pipe pressing hammer drilling of 8 160mm pipes. Construction of pump house with, among other things, the following work steps: Sandwich element: 1,080 m2 Steel frame: 34,000 kg Reinforcement: 61,000 kg: Concrete: 280 m3