NYAB Plc’s financial statement release 2023: Strong growth in cash flow and order backlog

28.02.24

October-December in brief

  • Revenue amounted to EUR 87.8 (89.8) million, representing a change of -2.1%. In constant currencies, revenue growth was 1.3%.
  • EBITDA was EUR 8.6 (20.8) million, amounting to 9.8% (23.1%) of revenue. Comparison period includes sales gain from Skarta Energy transaction of EUR 14.7 million on EBITDA.
  • Operating profit (EBIT) was EUR 6.6 (19.2) million, amounting to 7.5% (21.4%) of revenue
  • Free cash flow was EUR 16.8 (9.5) million
  • Net debt/EBITDA was -0.3
  • NYAB signed a contract with an estimated value of EUR 89 million regarding the construction of Aurora Line and a contract with an estimated value of EUR 69 million to construct a solar farm in Utajärvi, Northern Ostrobothnia
  • Order backlog improved 23.0% and amounted to EUR 294.7 (239.7) million.

January-December in brief

  • Revenue amounted to EUR 280.4 (253.3) million, representing a change of 10.7%. In constant currencies, revenue growth was 16.6%.
  • EBITDA was EUR 21.4 (30.4) million, amounting to 7.6% (12.0%) of revenue. Comparison period includes sales gain from Skarta Energy transaction of EUR 14.7 million on EBITDA.
  • Operating profit (EBIT) was EUR 15.2 (25.7) million, amounting to 5.4% (10.2%) of revenue
  • Free cash flow was EUR 22.3 (3.7) million
  • The Board of Directors proposes a capital repayment of EUR 0.014 (0.007) per share, of which EUR 0.008 per share is ordinary profit distribution and EUR 0.006 is extraordinary profit distribution and which equals approximately EUR 9.9 (4.9) million, to be paid for shareholders.
  • NYAB gives a financial guidance where its revenue and operating profit for 2024 are expected to increase from 2023.

This announcement is a summary of NYAB Plc’s financial statement release January-December 2023. The complete release is available here. The information presented in the financial statement release is based on the audited financial statements for 2023.

CEO Johan Larsson’s review

NYAB accomplished great progress during 2023. We developed both our core business and our support functions, which included preparations for a future as a company listed in Stockholm. With this work, we have built a platform for future profitable growth.

Our reported growth was 10.7 percent and growth in constant currencies amounted to 16.6 percent. We maintained a healthy EBIT-margin of 5.4 percent and achieved a significant improvement in our free cash flow that amounted to EUR 22 million. In addition, we ended the year with a net cash position and the highest year-end order backlog ever, EUR 295 million, which provides a solid foundation going forward.

Our positive development should also be seen in the context that year 2023 was full of macroeconomic headwinds. Our customers were especially affected by inflation and uncertainties regarding interest rates. Hence, investments in our markets were practically frozen during our seasonally highest period between May and October. Several contracts that were expected to be signed during the first half of the year were delayed. It is satisfying to see that, despite these challenges, we stayed committed to our most important supporting pillar, not to grow with increased risk. Therefore, our growth was modest in NYAB measures, and we decided not to complete any M&A’s due to uncertainties in the market.

Stabilization of the macroeconomic environment towards the end of the year restored confidence among our customers, which resulted in a significant order intake during the fourth quarter. We signed our largest contracts ever regarding the construction of Aurora Line, a 400 kV transmission line between Sweden and Finland, and a 102.5 MWp solar farm in the municipality of Utajärvi in Northern Ostrobothnia. Estimated values of these projects are EUR 89 million and EUR 69 million, respectively, and they are good examples of our work to enable green transition in the Nordics.

Since the fourth quarter, we have noticed that all our markets are improving, and we currently see a strong demand in all our sectors. The most relevant global megatrends – green transition, de-globalization, and urbanization – heavily drive investments in the energy sector, where our growth is the fastest, as well as infrastructure and industry sectors.

To summarize, we achieved good growth and cash flow, as well as a strong margin in relation to our industry. Together with an all-time high backlog at the end of the year, we proved the scalability in our business model for the tenth consecutive year. To achieve all this in an extremely challenging environment says a lot about us and our favorable position in the market. We will continue to build value for our customers, employees, and shareholders in accordance with our new strategic plan, thus enabling the progress of society for future generations.

Finally, I want to thank NYAB’s employees who are working diligently to make us a better company every day. I am proud of the accomplishments that have been demonstrated throughout the year through your competence, dedication, and teamwork. Together, as one team, I am confident that we will continue to achieve even more in the coming years.

Future outlook

NYAB sees its record-high year-end order backlog together with its exposure to growing sectors and geographical markets as a basis for a positive outlook. NYAB gives a financial guidance where its revenue and operating profit for 2024 are expected to increase from 2023.

Global megatrends, such as green transition and urbanization, also provide robust demand for NYAB’s business areas. The transition of volumes to 2024 from 2023 due to late year winter conditions, as well as the stabilization of inflation and interest rate development at the end of the year, further support the solid foundation for the 2024 outlook.

Key uncertainties impacting the business and financial performance include the development of inflation, interest rates, and value of the Swedish krona, weather conditions, as well as the functionality of supply chains and other typical project risks.

The long-term outlook is positive for all business areas and NYAB is well positioned to deliver in accordance with its long-term financial targets.

Green transition accelerates the construction of renewable energy and power networks, as fossil fuels are being replaced and demand for energy increases with the electrification of industrial processes. Besides the rapidly growing wind power, an increasing number of industrial-scale solar farm projects is proceeding to the construction phase, and investment plans of main grid companies amount to several billions of euros.

Regarding infrastructure, there are large investment needs in the public sector for both transportation and water treatment, and urbanization increases demand especially in the Stockholm-Mälardalen region. Significant opportunities within industrial clients are expected, among others, in the mining industry that is essential for rapidly growing clean energy technologies especially in NYAB’s key market in Northern Sweden.

Management webcast

NYAB arranged a management webcast after the publishing of the financial statement release. Recording of the webcast, where CEO Johan Larsson and CFO Aku Väliaho presented financial information and significant events for the financial year 2023, is available below.

Read more

NYAB Södertälje

NYAB undertakes extensive water work in Södertälje Canal

Read more

Meet Supervisor Enna Ruonala & Quality Manager Hanna-Kaisa Vesa

Read more

NYAB wins turnkey contract for railway project

Read more

NYAB Plc’s Annual Report 2023 and Notice to the Annual General Meeting

Read more

NYAB plans to carry out re-domiciliation to Sweden through a cross-border conversion and has applied for the delisting of its shares from Nasdaq First North Growth Market Finland

Read more

NYAB signs letter of intent to acquire marine construction company

Read more

Meet Patrik Nilsson – Business and Estimating Manager at NYAB Mälardalen

Read more

Meet Patrick Kraft – Site Manager at NYAB

Read more

NYAB signs turnkey contract for Duroc Rail AB’s new industrial building at Luleå Industrial Park

Read more

NYAB signs contract with Swedish Transport Administration for additional projects within Opto 2.0

Read more

NYAB receives additional order from LKAB in urban relocation project

Read more

Olli-Pekka Purhonen

Meet Olli-Pekka Purhonen – Solar Power Construction Project Director

Read more

Meet Martin Wäppling – Work Manager at NYAB

Read more

Mattias Broström appointed CEO of NYAB Infrastruktur

Read more

Sijoittajat -sivun kuvituskuva

NYAB approves revised long-term financial targets and a new strategic plan for 2024–2026

Read more

NYAB to construct solar farm developed by Skarta Energy to Utajärvi

Read more

Meet Karin Engfors – Site Manager at NYAB

Read more

NYAB’s Q3/2023: Improved profitability

Read more

NYAB signs a contract for an extensive power line work in Luleå

Read more

Pauli Lahti

Meet Pauli Lahti – Sales Manager at NYAB

Read more

NYAB signs a significant agreement to start constructing Aurora Line

Read more

Hanna-Kaisa Vesa

Quality at every step

Read more

Meet Lina Lundqvist – Construction Engineer at NYAB

Read more

Fingrid 100 kV sähköasema

NYAB to build a 110kV substation for Fingrid in Loimaa

Read more

Meet Göran Sandberg – Measurement Coordinator at NYAB

Read more

Kalajoen Hiekkasärkkien liittymän alikulku

Infrastructure team working diligently in North Ostrobothnia

Read more

NYAB is preparing move to Sweden – Jan Öhman as new Chairman of the Board

Read more

Elin Åhrberg

NYAB appoints Elin Åhrberg as a new member of the Executive Management Team

Read more

Veli-Matti Kumpula

Meet Veli-Matti Kumpula – Site Manager at NYAB

Read more

NYAB begins work for Talga at Europe’s first commercial battery anode refinery

Read more

NYAB Plc’s half-yearly report 2023 – latest videos and management views

Read more

NYAB Plc’s half-yearly report and management webcast: Strong growth and development despite macroeconomic headwinds

Read more

Jenni Autio toimii NYABin työmaalla työnjohtajana

Traveling fuels interest in work

Read more

Meet Fredrik Fällback – Site Manager at NYAB

Read more

Meet Victor Tanndal – Work Manager at NYAB

Read more

NYAB signs a framework agreement with Stockholm Vatten & Avfall

Read more

Meet Ronny Toma – Work Manager at NYAB

Read more

NYAB implements expansion projects of Utanen and Isokangas 110kV substations in Northern Ostrobothnia

Read more

Antti Keskinen, Liiketoimintayksikön johtaja, Sähköverkkorakentaminen | NYAB

Green transition speeds up NYAB’s electricity transmission network operations

Read more

Anton Sandgren – Site Manager at NYAB

Read more

NYAB signs two new contracts with Svenska kraftnät

Read more

Ensuring safety through cooperation

Read more

NYAB wins SEK 66 million contract at Arlanda for Swedavia

Read more

NYAB wins two contracts in Kiruna municipality – infrastructure projects for Infranord

Read more

NYAB as the company of the month

Read more

Matilda Stjärnström – QHES Manager, NYAB Sverige

Read more

NYAB Plc: Annual report 2022 has been published

Read more

NYAB infrastruktur, järnväg, vägarbete

NYAB signed 10 MEUR agreement with Swedish Transport Administration

Read more

NYAB Plc’s financial statement release 2022 and management webcast

Read more

Over EUR 13 million in investment aid for Skarta Energy’s solar farm to be built in Utajärvi

Read more

NYAB and Energiequelle sign BoP contract for Mikonkeidas wind farm

Read more

NYAB approved as a builder of transmission lines in Fingrid’s supplier register

Read more

NYAB signs a contract to prepare for the construction of Aurora Line

Read more

Skarta Energy and Solarigo’s 61 million euro solar farms project enabled by investment aid

Read more

NYAB-logo

SkartaNYAB renamed to NYAB

Read more

Vastuullisuus noston kuva

SkartaNYAB establishes a joint venture with CapMan fund to construct renewable energy producing facilities exceeding 500 MW

Read more

SkartaNYAB Plc changes its name to NYAB Plc and sets strategic objectives for 2022-2024

Read more

Fingrid concludes first solar power plant connection agreement with Skarta Energy – Utajärvi project moves forward

Read more

NYAB was accepted into Fingrid’s supplier register

Read more

Skarta and Tohmajärvi municipality to begin cooperation – Eastern Finland’s largest energy project under planning

Read more

Utajärvi

Skarta’s Near Energy project in Utajärvi is progressing – action permit for a solar power plant and Horizon research funding from the EU

Read more

SkartaNYAB strengthens its position on the energy construction market in Norrbotten by acquiring Power Forze AB

Read more

Sitema has been awarded ISO 9001, 14001 and 45001 certificates

Read more

SkartaNYAB and Uusiutuva Energia Karahka Oy have signed a BoP agreement for a Karahka wind park in Oulainen

Read more

Skarta will build a wind farm in Pajuperänkangas with a new customer, ABO Wind

Read more

UKI Arkkitehdit Oy

Skarta signed a contract with SSAB regarding construction project of new office building, as well as research and laboratory facility, to Raahe plant

Read more

Skarta and the Centre for Economic Development, Transport and the Environment for Lapland signed an extensive contract on the Jokikylä bridge in Oulu

Read more

SkartaNYAB has signed a comprehensive framework agreement with the Swedish Transport Administration

Read more

Skarta signs two contracts with LKAB for the execution of infrastructure projects

Read more

Skarta will be making everyday life effortless and clean also in Pirkanmaa – Skarta was awarded the contract for the building of pumping stations for Tampere Region Central Wastewater Treatment Plant

Read more

NYAB wins customer trust

Read more

NYAB signs extensive agreement with Piteå municipality

Read more

Magnus Granljung takes over as CEO of NYAB

Read more

The strongest actors in solar energy to cooperate – Skarta and Solarigo aim to build 1,000 megawatts of solar power

Read more

Skarta founded a new business unit – electrical grid business to complement the value chain

Read more

vidja

NYAB moves cultural buildings on behalf of LKAB

Read more

vidja

NYAB signs framework agreement with Huddinge municipality

Read more

vidja

NYAB is awarded three projects in the Ore Fields

Read more

NYAB is awarded an energy project in Umeå

Read more

NYAB is awarded the “Operating area Överkalix & Övertorneå” by the Swedish Transport Administration

Read more

Tuulivoimalan perustukset raudoitustyön alkuvaiheessa Juurakon tuulipuistossa Kalajoella. Laadunvarmistus on olennainen osa työvaihetta, ja siihen mennessä työmaalla on dokumentoitu jo monta suunnitelmaa ja pöytäkirjaa.

Quality is the basis of everything for Skarta

Read more

Skarta joins forces with Swedish NYAB Group to step up the pace of building a clean future

Read more

Skarta, builder of a clean future, developed a model for the calculation of CO2 emissions that relate to the infrastructure of wind farms

Read more

NYAB contracted for projects in Stockholm and Umeå

Read more

Near Energy at the center of the development of Skarta’s energy business

Read more

vidja

NYAB is awarded an infrastructure contract worth 130 million for Huddinge municipality

Read more

Skarta aims at being at the forefront of hydrogen economy – acquires the first new-generation hydrogen car in Finland for its use

Read more

NYAB wins assignments in the Stockholm area

Read more

First of its kind in Finland – Skarta had a major role in the closure of the Hitura mine

Read more

The bridge over Siikajoki, built by Skarta, was opened to traffic

Read more

Skarta completed the construction work for the Jämsä central sewage treatment plant three months early

Read more

New project for Skarta in Metsä Group’s bioproduct mill site

Read more

NYAB is building a wind farm in Kalajoki at full power

Read more

Skarta has launched new financial targets and strategic main directions – Activities will be expanded towards overall projects in wind power, solar energy, and hydrogen solutions

Read more

Trading in Skarta Group Plc’s new shares began on the First North marketplace

Read more

Skarta’s journey to become a First North company is progressing according to plan – the Board of Directors to have strong expertise in the energy sector

Read more

Skarta got an order worth MEUR 10 from LKAB

Read more

Skarta to build the foundations for EPV Energia’s wind farm in Närpiö

Read more

NYAB wins the Group’s largest contract of all time

Read more

Kuvituskuva, nainen ja mies tietokoneella

Job opportunities at Skarta

Read more

vidja

NYAB is awarded assignments by Nacka municipality and the Swedish Fortifications Agency in Kiruna municipality

Read more

Skarta Group seeks momentum for growth on the stock market

Read more

Skarta to partner with Atria on a major wind power project

Read more

NYAB is building a new road and bridge for Skellefteå municipality

Read more

Skarta Energy Oy to be a new wind power subsidiary

Read more

NYAB is awarded a bridge contract in Stockholm

Read more

Skarta Finland started work on the construction site of the Kemi bioproduct factory

Read more

HS-Vesi invests in Paroinen treatment plant in Hämeenlinna

Read more

VSB selected NYAB as the main contractor for the Juurakko wind farm

Read more